A busy trading floor was experiencing difficulties with their six air handling units, which were fed from a single 480V, 400-amp service. The units were malfunctioning, stalling and at times were unable to start, causing the temperature in the control room to rise to unacceptable levels. A Dranetz Power Platform PP4300 was installed for a two-week period to evaluate the voltage and current of the 400-amp service feeding the handlers.

Overloaded Service Case Study

Based on the collected data, we learned the following:

  • The top graph shows the voltage, which averages about 450V as opposed to the 480V expected. This resulted in a continual undervoltage situation, putting the system at a higher susceptibility for sags.
  • Three large sags, greater than 10% of nominal occurred (see purple arrows), and numerous sags at around 5% do valor nominal.
  • O gráfico inferior mostra a atual, esperado que fosse 400 amps. Como você pode ver, em inúmeras ocasiões ele subiu acima 400 A, e em vários casos subiu para 500 A.
  • O aumento da corrente pode ser correlacionado com afundamentos de tensão.

Overloaded Service Case Study

No acima, vemos que a tensão (em vermelho) e o atual (em azul) ambos estão diminuindo, indicando que a origem do afundamento pode ser encontrada a montante do ponto de monitoramento (Regra QP #1). Como resultado desta pesquisa, dois dos manipuladores de ar foram transferidos para um serviço diferente, eliminando uma condição de circuito sobrecarregado e uma fonte de quedas de tensão.