Category Archives: Case Study

Active Harmonic Filters In Printing Applications

Harmonics causes problems in printing plant

Harmonic Filter Restores Power Quality and Reduces Downtime Caused by Harmonics

Problems with power quality often become apparent through problems in production and surrounding equipment such as lighting.

This is what happened at one of the largest printers in Holland.

Background

Line to line voltage with Active Harmonic Filter

Line to line voltage with Active Harmonic Filter

The printing company consists of two printing plants located in Amsterdam. The plant employs 170 people, producing six daily newspapers and several other free local papers and magazines. The plant prints up to 1 million papers every day with printing presses running almost nonstop.

Poor Power Quality – the Challenge

The printers had been struggling with power quality problems for many years. Flourescent lighting had to be changed continuously as the tubes kept failing. The electrical ballast had to be changed every six months instead of every 5 years. This kept one employee busy 2-3 days a week. In 2011 just the lighting problems and other broken components cost the printers about

300 000 €. In addition to these losses, the plant had power quality related problems during startup of the presses, which resulted in additional losses through production downtime.

Active Harmonic Filters – the Solution

Line to line voltage with Active Harmonic Filter

Line to line voltage with Active Harmonic Filter

The printing group decided on an investment in power quality and quite literally, a brighter future. Six harmonic filters with a total compensation current of 1800 A were installed to optimize the power grid and reduce harmonics.

Harmonic Filtering Gave Quick Results

Following installation and commisioning of the active harmonic filters all previous problems disappeared. The printing plant can nowuse their printing presses without disturbances from poor power quality. Due to the continuous stops in production and equipment failure, which had been a daily occurrance, the return on investment for the harmonic filtering system was very short.

Smooth sailing for cruise ship terminal (Reliable Power Inc.)

Marco Polo Cruise Ship Terminal | Saint John Port Authority

The Scenario

In 2009 the Saint John Port Authority was scheduled to host over 190,000 passengers & guests from over 74 cruise ship vessels. The Pugsley A&B terminals were renovate on the city`s waterfront and would be the home of the new Marco Polo Cruise Terminal.

The Challenge

With the advent of new fire protection and life safety codes, the passenger’s safety would be pertinent and use of an Emergency Lighting Inverter would be part of the terminals essential services. When applying the emergency egress lighting system, it is imperative to meet CSA, UL924 and NFPA 101 requirements. The life safety system must be able provide a sufficient lighting runtime to safely evacuate all passengers from the building.

The Solution

The system shall incorporate an on-line, dual conversion, microprocessor controlled, high frequency, IGBT PWM rectifier/charger and inverter, high speed automatic bypass transfer device, battery charging system, energy storage battery platform, an advanced, full diagnostic, monitoring and testing system with touch screen LCD display panel, and all the related hardware components and software to facilitate a functional centralized system. The emergency power supply system shall provide immunity from all line disturbances and power interruptions. The system shall include an uninterrupted, normally on output power section and provisions to include a normally off standby output power section, thus enabling compatibility with emergency lighting fixtures operating in normally on and standby mode(s). A self-diagnostic monitoring alarm system shall continuously advise of system status and battery condition.

Summary

In January 2009 the Centralized Emergency Lighting Inverter was successfully commissioned and tested on-site by Reliable Power Systems Inc. It now provides a 90 minute run time for the safe evacuation of the Marco Polo Cruise Terminal. For more information about this application please feel free to contact our office anytime.

Source : Reliable Power

Call Toll-Free: 1-800-533-1337

Email: info@reliablepower.ca

First quality solutions for our First Nations (Reliable Power Inc)

Maritime First Nations Communities

The Scenario

The 2009 flu pandemic was a global outbreak of a new strain of H1N1 influenza virus, often referred to as “swine flu”. With the potential danger of this outbreak there had to be mass amounts of vaccine produced and distributed across the country in a very short period of time.

The Challenge

Remote and isolated First Nations communities, have higher than the national average incidence of underlying chronic medical conditions, putting them at increased risk of severe illness from H1N1 infection. Some of these communities face other public health challenges, such as overcrowding, that may increase the opportunity for H1N1 Flu Virus to spread.

A further concern for people living in remote areas is that if someone does have an adverse reaction from the H1N1 Flu Virus, it may take some time to be transported to a hospital should they need hospitalization. This is especially true for fly-in communities, which is why getting a vaccine is highly recommended for all people in remote communities.

With Limited supply of the vaccine to each area/clinic there was no room for error and there had to be additional precautions taken to insure there would be no loss of vaccination do to uncontrolled situations such as power loss.

The challenge here was to provide a power backup for the vaccine fridges to ride-through potential long term power outages.

The Solution

Reliable Power was selected to supply model MP2000 dual conversion on-line UPS systems rated 2000VA/1400W complete with external batteries modules providing up to 24 hours runtime in the event of power loss.

Summary

Throughout the Fall and Winter a roll out of this UPS and Batteries were installed in various First Nations communities in Nova Scotia, New Brunswick & Newfoundland including; Burnt Church, Eel River Bar, Indian Brook, Paq’tnkek, Saint Mary’s, Sheshatshui Innu, and We’koqma’q which now allows the heath centres to maintain a safe supply of the flu vaccine for up to 24 hours during a power outage.

Source : Reliable Power

Call Toll-Free: 1-800-533-1337

Email: info@reliablepower.ca

Reliable Power keeps research afloat (Reliable Power Inc.)

St. Andrews Biological Station

The Scenario

Canada’s first marine biological research station began operations as a temporary, floating laboratory, in St. Andrews in 1899. Over the past century, the St. Andrews Biological Station (SABS) has become recognized nationally and internationally for its contributions to marine science.

The Challenge

St. Andrews Biological Station maintains a reservoir, the water for this reservoir is pumped from the ocean with two large 100 HP pumps into a large pool which is then filtered and pumped into the reservoir. The speed and flow rate of these pumps is controlled by VFD (Variable Frequency Drives). These VFD inherently pollute the electrical system especially in remote sites where the electrical grid is considered soft and the presences of harmonic distortion is more common.

The challenge here is that due to all the research computer systems onsite (over 125 pc’s) would no doubt be affected by these high level of harmonics. Harmonic currents increase losses, overheat equipment, and interact with the distribution system impedances causing voltage distortion which can have a detrimental effect on all equipment connected to the system (ie: the research computers)

The Solution

Reliable Power worked with the electrical authority at the site and supplied Harmonic Filters manufactured by Mirus International Inc. These AUHF (Advanced Universal Harmonic Filters) or Lineators mitigated the current distortion to levels meeting IEEE519. These Lineators are a revolutionary advance in the area of passive harmonic mitigation. NO other device on the market can meet the stringent limits of the IEEE Std 519 at any equivalent efficiency, size and cost.

Summary

The Mirus Lineators are now successfully operating at the Biological Station and the research computers are now protected from the harmonics caused by the VFDs. For more information about this application please feel free to contact our office anytime.

Source : Reliable Power

Call Toll-Free: 1-800-533-1337

Email: info@reliablepower.ca

Making wind power more reliable (Reliable Power Inc.)

Application of a UPS within a Wind Power Substation

The Scenario

Newfoundland and Labrador Hydro in conjunction with NewWind Group Inc. partnered to install a 27-megawatt farm in St. Lawrence featuring nine, three-megawatt wind turbines that generates roughly 100,000-megawatt hours a year – enough to provide electricity to approximately 6,800 homes.

Successful operation and protection of the wind farm substation requires reliable operation of the protection and control systems. The protective devices are used to detect faults on the network and operate circuit breakers to isolate any faults. Tripping and re-closing of substation breakers in a fault situation is a common mode of operation. Rapid fault detection and isolation is a requirement for connection to the grid avoiding cascading failures or complete loss of the grid network; thus the need for an AC & DC UPS system.

The Challenge

In the spring of 2008 Reliable Power Systems Inc responded to a RFQ to supply and deliver an indoor inverter and battery/charger system to support both the DC & AC loads.

The 125volt DC loads consists of:

  • Substation circuit breaker
  • Protection relays
  • Substation SCADA (Supervisory Control and Data Acquisition) system

The 125volt AC loads consists of:

  • Telecommunication equipment
  • Lighting circuits
  • Vestas wind turbine SCADA Systems

The Solution

After reviewing the application requirements with contractor the contract was awarded to supply the following material:

HV Series Uninterruptible Power Supply (UPS) System

Marathon VRLA (Valve-Regulated-Lead-Acid) batteries

The UPS system is a line interactive design incorporating an IGBT based microprocessor controlled PWM inverter, high speed transfer SCR devices, constant voltage regulating transformer and battery charger. The UPS provides complete load immunity from all line disturbances and power interruptions with no loss or disruption in AC output power.

This solution was proven to be the most cost effective while offering a standard of-the-shelf well proven and tested design. The rugged HV Series UPS operates on a nominal 120vdc buss. The 20-amp internal charger provides rapid recharge current to the batteries while providing the “standing” DC Loads of approximate 5 amps. The HV Series AC output rating of 14,000va/10,000watts provides more than ample power to the substation AC loads.

The Marathon battery plant is made up of two separate strings of ten 12volt (10 x 12 = 120vdc) battery modules. The two strings provide redundancy and are mounted on the same rack. These M12V125F batteries provide high performance and reliability. The front positive and negative terminals; greatly facilitates both installation and maintenance.

Summary

In August of 2008 the UPS module and battery banks were successfully commissioned and tested on-site by Reliable Power Systems Inc. For more information about this application please feel free to contact our office anytime.

Source : Reliable Power

Call Toll-Free: 1-800-533-1337

Email: info@reliablepower.ca

Reliable Power keeps Goose Bay flying (Reliable Power Inc.)

Canadian Forces Base Goose Bay

The Scenario

Canadian Forces Base Goose Bay (5 Wing Goose Bay) is operated by the Canadian Forces Air Command. Since its initial development during World War II, the air forces of several nations have used CFB Goose Bay as a base for NATO flight training.

The base remains active today. It is designated as an alternate emergency landing site for the space shuttle, and operates in conjunction with the civilian Goose Bay Airport.

The Challenge

In the movement to attract more use of the facilities at 5 Wing Goose Bay, Hangars 7 & 8 were to update the “ground support” power for the aircrafts while undergoing maintenance in the hangars.

Modern military aircraft are equipped with powerful radars, sensors, weapon systems, and sophisticated cockpit displays that require large amounts of electricity to operate. Commercial airliners too must provide power for environmental systems, galley equipment, cockpit displays, communication gear, weather radar, and in-flight entertainment systems. DC power supplies are insufficient to meet the demands for electricity to operate flight instruments, actuators, heating equipment, avionics, and internal/external lighting on these large aircraft. These planes instead use alternating current (AC) systems that usually supply 115 volts at 400 hertz.

The Solution

Reliable Power was commissioned to provide the following:

  • 90kva Solid State Frequency Converter
  • Motorized Cable Retriever for 400Hz aircraft cable with output of 90kva
  • Solid State 28 vdc power supply
  • Diesel Power Combination Power Cart 90 Kva 400hz and 28 vdc 1000A cont. 2500A peak

The above was provided for both Hanger 7 & 8 at 5 Wing Goose Bay.

Summary

In August of 2010 the Frequency Converters and Cable Retrievers were successfully commissioned by Reliable Power Systems Inc and now provide 5 Wing Goose Bay with ground support power which is in use today. For more information about this application please feel free to contact our office anytime.

Source : Reliable Power

Call Toll-Free: 1-800-533-1337

Email: info@reliablepower.ca

Reliable Power keeps airport online (Reliable Power Inc.)

Halifax International Airport Authority

The Scenario

As part of the main incoming power distribution continuous upgrade underway at Halifax Stanfield International Airport, the Halifax International Airport Authority (HIAA) identified a requirement for one (1) 125Vdc station battery and one (1) 125Vdc station battery charger. HIAA requests qualified firms review their project requirements and provide quotations for the supply and delivery of the equipment as specified.

The Challenge

The HIAA requires the extensive use of the substation throughout the network. The purpose of the substation is to provide voltage transformers, switching and protection. The protective devices are used to detect faults on the network and operate circuit breakers to deflect the fault.

The Solution

The key to successful operation and protection of the substation and downstream network is the reliable operation of the protection and control systems. HIAA choose Reliable Power to provide one (1) 125Vdc battery and one (1) 125Vdc station battery charger which would provide an ongoing power source for the Substation.

Summary

In September of 2010 the charger and battery bank was successfully commissioned by Reliable Power Systems Inc and now provide HIAA a crucial power supply which is in use today. For more information about this application please feel free to contact our office anytime.

Source : Reliable Power

Increasing Power Supply Reliability

This section carries case studies on how to obtain high reliability power supply for sensitive processes and mission critical applications.

Voltage Fluctuations and Flicker (John Wiley & Sons, Ltd)

Author: Araceli Hernández Bayo

Source: Handbook of Power Quality Edited by Angelo Baggin, John Wiley & Sons, Ltd

1.0) EVALUATION OF THE CONNECTION OF A THREE-PHASE WELDING MACHINE

This example shows a study of flicker prediction based on simplified assessment methods oriented at evaluating the connection of a new fluctuating load to an existing network.

Figure 1 shows the diagram and data of the 15 kV supplying network. An industrial customer using a large welder (called W1 in Figure 1) has requested the connection of an additional welding machine to increase production capacity. The aim of the study is to decide on the connection of this new load bearing in mind that the Pst planning level of the utility for MV systems is 0.9.

As can be observed, the MV line feeding the disturber client is also feeding other loads (consumer 2) which are residential and office-building consumers considered as non­disturbers (i.e. as non-fluctuating loads). Consumer 1, connected at the point indicated as PCC1, also has non-fluctuating loads.

Different flicker measurements have been performed in order to identify the background flicker levels at PCC2 and the flicker contribution of the already operating welder 1. By these measurements, it has been observed that, when welder 1 does not operate, the background short-term flicker severity at PCC2 is 0.30. When welder 1 is running, the flicker severity level at PCC2 is 0.67.

Figure 1 Schematic diagram of the supplying network under study

Figure 1 Schematic diagram of the supplying network under study

The new welding machine whose connection is under study has the following characteristics:

  • The power absorbed during the melting phase of the welding operation can reach 1800 kVA with a power factor of 0.85. The power absorbed during two welding periods is negligible.
  • The dwell time is 1.5 s and the repetition time is 3 s; that is, welding periods last 1.5 s and are followed by 1.5 s of no load. Therefore, 20 welding operations are performed per minute, which mean 40 voltage changes per minute.

The duty cycle of both welders is around 30 minutes per hour. Therefore, this study will focus on the analysis of short-term flicker severity, Pst, as it will be a stronger requirement than Plt.

The study is organized in the following steps:

  1. Calculation of flicker severity caused at PCC2 by welding machine 1.
  2. Calculation of the voltage change caused at PCC2 by the connection of the welding machine under study (W2).
  3. Estimation of the flicker severity caused at PCC2 by welding machine 2.
  4. Summation of the Pst caused at PCC2 by the simultaneous operation of both machines.
  5. Analysis of solutions.

1.1) Flicker Severity Caused at PCC2 by Welding Machine 1

The Pst level caused by the individual operation of welder 1 can be estimated by means of the measurements performed at PCC2 when the welding machine is working, PstPCC2withW1, and when the welder is not working, PstPCC2withoutW1. Assuming that the disturbance created by the welder and the disturbance introduced by the background level are unrelated disturbances, a cubic summation law can be used to make this estimation:

Voltage Fluctuations and Flicker 2

Pst1 is the flicker severity contribution of welder 1 to the global Pst level at the point of connection PCC2.

1.2) Voltage Change Caused by the New Welder

Before calculating the voltage change caused by the operation of the welding machine, it is necessary to determine the source impedance at the point of common coupling of this equipment. This is done by means of the following calculations:

• Source impedance. As indicated in Figure C5.1, the short-circuit power of the network in 66 kV is 600 MVA. Therefore, the source impedance expressed on the 15 kV side is

Voltage Fluctuations and Flicker 3

A ratio of 30 will be assumed between the reactive and the resistive part of the source impedance. Therefore, the complex form of the source impedance is

Voltage Fluctuations and Flicker 4

• HV/MV transformer impedance. The transformer has a rated power of 50 MVA, an inductive impedance of 10 % and a resistive impedance of 0.8 %. Therefore the transformer impedance is calculated as

Voltage Fluctuations and Flicker 5

• MV line impedance. The resistance of the underground MV cable is 0.125 i/km and the reactance is 0.104 i/km. The length of the line is 2.5 km. Therefore, the complex impedance of this line is

Voltage Fluctuations and Flicker 6

Therefore, the total impedance at PCC2 is

Voltage Fluctuations and Flicker 7

This value implies that a short-circuit power of approximately 200 MVA is available at PCC2. The analyzed additional welder causes power variations of 1800 kVA which represent 0.9 % of this short-circuit power. This is a value high enough to require a detailed evaluation of the flicker emission levels introduced by this additional load.  At this rate of voltage variations per minute, Technical Report IEC 61000-3-7 proposes a ratio of 0.2 % between the power variation of the load and the short-circuit power for approving the connection of the load to an MV system without any further analysis.

Active and reactive power variations (!P and !Q) caused by the additional welding machine can be calculated by making use of its known characteristics, namely the apparent power variation (1800 kVA) and the power factor (0.85). The voltage change produced by welding machine 2 at PCC2 can be calculated by applying Equation (5.12) as follows:

Voltage Fluctuations and Flicker 8

1.3) Estimation of the Flicker Severity Caused by Welding Machine 2

The repetition rate of the voltage changes caused by the welding machine is, as previ­ously indicated, 40 voltage changes per minute. Entering this value into the severity curve (Figure C5.2) for rectangular steps produces on the ordinate the voltage change do ≈0.9 (%) which leads to Psto=1.

Figure 2 Rectangular voltage variation for Pst = 1

Figure 2 Rectangular voltage variation for Pst = 1

Taking into account that short-term flicker severity is a linear parameter with respect to the magnitude of the voltage change that causes it, the expected Pst2 caused by the individual contribution of welder 2 for the voltage change calculated in (C5.9) isVoltage Fluctuations and Flicker 10

The expected Pst can also be calculated by means of the analytical approach presented in the publication IEC 61000-3-3 [1] that was discussed in Section 3.3. This method is based on calculating the flicker time, tf, by means of the following expression:

Voltage Fluctuations and Flicker 11

In this case, since voltage changes are rectangular, factor F is one unit. Therefore

tf = 23 07132 = 0769 s (C5.12)  manque celui-ci

Pst is determined by summing all the flicker times, tf, inside a 10 min time interval, Tp. Considering that 40 voltage changes occur per minute, i.e.Voltage Fluctuations and Flicker 12

the value of Pst2 calculated by means of this method is very close to the value obtained by means of the flicker curve, although a slight difference appears between them. This difference can be understood by bearing in mind that both approaches, although providing reasonable estimates, are based on simplifications.

1.4) Pst Caused by the Simultaneous Operation of Both Machines

In order to obtain the total flicker severity at point PCC2, the individual contribution of each disturbing load connected to this point (Pst1 and Pst2) together with the background flicker level (PstPCC1withoutW1), must be considered.

Therefore, assuming that the operation of both welders is uncorrelated, the summation law described in Section 5.3.3 can be applied with a coefficient m = 3. This assumption ignores the more severe flicker which would result from the coincidence of steps from different welders. In this case, since welding cycles last 3 s, this can be an acceptable assumption. Therefore, the global flicker emission at PCC2 is equal to

Voltage Fluctuations and Flicker 14

This value exceeds the utility planning level (Pst = 0.9) and, therefore, it is not tolerable. The connection of the additional welder machine is unacceptable, unless mitigation methods are provided.

1.5) Analysis of Solutions

A possible solution is to install a compensator device to reduce flicker emission of the welders. Another possibility is to reinforce the short-circuit power at the point of connection of the welders by building a new line. Although this can be an expensive solution, the technical analysis presented next shows the improvement achieved by means of this solution.

If a new underground cable, identical to the existing one, is connected in parallel with it between PCC1 and PCC2, the short-circuit power at PCC2 is increased. The new impedance of the equivalent parallel of both lines is

Voltage Fluctuations and Flicker 15

Therefore, the new total impedance at PCC2 is

Voltage Fluctuations and Flicker 16

The available short-circuit power at PCC2 is now 230 MVA.

Both welders have a power factor of 0.85 in the welding periods. Therefore, considering (C5.9), the ratio between the voltage changes caused in this new network configuration and the previous one is

Voltage Fluctuations and Flicker 17

This result implies that in this new situation, the Pst level caused by the individual contri­bution of each welder will be decreased by a ratio of 0.77. Assuming that consumer 2 connected at PCC2 is a non-disturber consumer, the background flicker level existing at PCC2 is propagating from the upstream voltage level and, therefore, it is not modified by the addition of the new line. Therefore, the new value of flicker severity is

Voltage Fluctuations and Flicker 18

The Pst level obtained by applying this solution is below the planning level, so this proposal is acceptable. It is important to note that this analysis is made using the assumption that the welders are the only fluctuating loads connected at the MV busbars.

An alternative approach for determining the individual emission limits of these welders could be based on calculating the quotient between their rated power and the total power of the loads directly supplied to the MV network. In such an analysis, the total flicker level acceptable at PCC2 should be shared between all the connected loads in proportion to their rated power.2

Nevertheless, in the situation analyzed in this case study, since consumer 1 and consumer 2 are non-fluctuating loads, this kind of approach would give place to very strict limits for the disturbing loads imposing flicker levels unnecessarily far below the planning levels. Therefore, under these circumstances, a more flexible method for assessment of individual limits has been applied, although it is convenient to bear in mind that future arrangements or changes in the flicker contributions of the connected customers should be carefully analyzed.  This evaluation criterion is known as ‘Stage 3’ in the context of Technical Report IEC 61000-3-7.

2.0) FLICKER MEASUREMENTS IN AN ARC FURNACE INSTALLATION

Arc furnaces are very fluctuating loads that produce stochastic flicker. The random nature of voltage fluctuations caused by arc furnaces complicates the use of simplified flicker prediction methods. A measurement campaign is a more precise way to assess flicker levels produced by this type of load.

This case study presents the Plt measurements that have been performed over several days in the arc furnace installation depicted in Figure 3. This installation is connected to a 110 kV network through a three-winding transformer whose data is indicated in Figure 3. The flicker measurements were performed over several days at the MV side.

Figure 4, Figure 5 and Figure 6 show the evolution of Plt at phase A, B and C, respectively, measured at the MV busbar.

Table 1 shows the main statistics of the Plt values measured at three phases over a week.

The Plt caused at buses upstream in a grid is reduced reciprocally to the increasing short-circuit power. According to the percent reactance values of the transformer of this installation, the available short-circuit power on the MV side, where the measurements have been carried out, is around 20 times lower than the short-circuit power available on the HV side of the transformer. Therefore, a reduction in the flicker-level emission of the arc furnace with a ratio of 20 can be expected on the HV side with respect to the values indicated in Table C5.1. This situation leads to acceptable flicker levels in the PCC.

Figure 3 Schematic diagram of the arc furnace installation

Figure 3 Schematic diagram of the arc furnace installation

Figure 4 Plt evolution (phase A) at the MV bus of the arc furnace installation (Courtesy of Prof. Zbigniew Hanzelka)

Figure 4 Plt evolution (phase A) at the MV bus of the arc furnace installation (Courtesy of Prof. Zbigniew Hanzelka)

Figure 5 Plt evolution (phase B) at the MV bus of the arc furnace installation (Courtesy of Prof. Zbigniew Hanzelka)

Figure 5 Plt evolution (phase B) at the MV bus of the arc furnace installation (Courtesy of Prof. Zbigniew Hanzelka)

 Figure 6 Plt evolution (phase C) at the MV bus of the arc furnace installation (Courtesy of Prof. Zbigniew Hanzelka)

Figure 6 Plt evolution (phase C) at the MV bus of the arc furnace installation (Courtesy of Prof. Zbigniew Hanzelka)
Voltage Fluctuations and Flicker 23

Table 1 Statistics of measured Plt values

BIBLIOGRAPHY

[1] Ashmole P., Quality of supply – voltage fluctuations. Part 2. Power Engineering Journal, April, pp. 108–117, 2001.

[2] Garcia-Cerrada A., Garcia-Gonzalez P., Collantes R., Gomez T., Anzola J, Comparison of thyristor-controlled reactors and voltage-source inverters for compensation of flicker caused by arc furnaces. IEEE Transactions on Power Delivery, vol. 15, no. 4, pp. 1225–1231, 2000.

[3] Hanzelka Z. et al., Comparative tests of flicker meters. Proceedings of CIRED. 17th International Conference on Electricity Distribution, Barcelona Spain, 12–15 May 2003. Technical Reports, Session 2, Paper no. 25, pp. 1–5.

[4] Hernandez A., Mayordomo J. G., Asensi R., Beites L. F., A new frequency domain approach for flicker evaluation of arc furnaces. IEEE Transactions on Power Delivery, vol. 18, no. 2, pp. 631–638, 2003.

[5] IEC 868, Flickermeter. Functional and design specifications, 1986.

[6] IEC 61000-4-15 (1997–11), Electromagnetic compatibility (EMC) – Part 4: Testing and measure­ment techniques – Section 15: Flickermeter – Functional and design specifications.

[7] IEC 61000-4-15-am1 (2003–01), Amendment 1 – Electromagnetic compatibility (EMC) – Part 4: Testing and measurement techniques – Section 15: Flickermeter —-Functional and design specifications.

[8] IEC 60050 (161), International Electrotechnical Vocabulary (IEV) – Chapter: Electromagnetic compatibility.

[9] IEC 61000-3-7 (1996–11), Electromagnetic Compatibility (EMC) – Part 3: Limits – Section 7: Assessment of emission limits for fluctuating loads in MV and HV power systems.

[10] IEC 61400-21 (2001–12), Part 21: Measurement and assessment of power quality characteristics of grid connected wind turbines.

[11] IEC 61000-3-3 (1994-12), Electromagnetic compatibility (EMC) – Part 3-3: Limits – Limitation of voltage changes, voltage fluctuations and flicker in public low-voltage supply systems, for equipment with rated current ≤16 A per phase and not subject to conditional connection.

[12] IEC 61000-3-5 (1994–12), Electromagnetic compatibility (EMC) – Part 3: Limits – Section 5: Limitation of voltage fluctuations and flicker in low-voltage power supply systems for equipment with rated current greater than 16 A.

[13] IEC 61000-3-11 Ed. 1 (2000–08), Electromagnetic compatibility (EMC) – Part 3: Limits – Section 11: Limitation of voltage changes, voltage fluctuations and flicker in low-voltage power supply systems. Equipment with rated current ≤75 A and subject to conditional connection.

[14] IEC 61000-4-30 Ed. 1 (2003–02), Electromagnetic compatibility (EMC) – Part 4-30: Testing and measurement techniques – Power quality measurement methods.

[15] Larsson T. and Ekstrom Å., A PWM-operated voltage source converter for flicker mitigation. European Power Electronics Conference ’97, Vol. 3, pp. 1016–1020, September 1997.

[16] De Lange H., Experiments on flicker and some calculations on an electric analogue of the foveal system. Physica, vol. 18, pp. 935–950, 1952.

[17] De Lange H., Eye’s response at flicker fusion to square-wave modulation of a test field surrounded by a large steady field of equal mean luminance. Journal of the Optical Society of America, vol. 51, pp. 415–421, 1961.

[18] Mayordomo J. G., Prieto E., Hernández A., Beites L. F., Arc furnace characterization from an off-line analysis of measurements. Proceedings. Ninth International Conference on Harmonics and Quality of Power, 1–4 October 2000, Vol. 3, pp. 1073–1078, 2000.

[19] Mendis S. R., Bishop M. T., Witte J. F., Investigations of voltage flicker in electric arc furnace power systems. Industry Applications Society Annual Meeting, Denver, October, Vol. 3, pp. 2317–2325, 1994.

[20] Mombauer W., Calculating a new reference point for the IEC-Flickermeter. European Transac­tions on Electrical Power, vol. 8, no. 6, pp. 429–436, 1998.

[21] Montanari G. C., Loggini M., Pitti L., Tironi E., Zarinelli D., The effects of series inductors for flicker measurement in electric power systems supplying arc furnaces. Industry Applications Society Annual Meeting, 2–8 October 1993, Conference Record, Vol. 2, pp. 1496–1503, 1993.

[22] Rashbass C., The visibility of transient changes of luminance. Journal of Physiology, vol. 210, pp. 165–186, 1970.

[23] Reed G. F., Greaf J. E., Matsumoto T., Yonehata Y., Takeda M., Aritsuka T., Hamasaki Y., Ojima F., Sidell A. P., Chervus R. E., Nebecker C. K., Application of a 5 MVA, 4.16 kV D-STATCOM system for voltage flicker compensation at Seattle Iron and Metals. IEEE Power Engineering Society Summer Meeting, July, Vol. 3, pp. 1605–1611, 2000. Schauder C., STATCOM for compensation of large electric arc furnace installations. IEEE Power Engineering Society Summer Meeting, July, Vol. 2, pp. 1109–1112, 1999.

[24] Simons G., Das Flackern des Lichtes in elektrischen Beleuchtunganlages. ETZ, no. 37, pp. 453–455, 1917.

[25] UIE (Union Internationale d’Electrothermie), Flicker Measurement and Evaluation, Technical Report, Second Edition, 1991.

[26] UIE (Union Internationale d’Electrothermie), Connection of Fluctuating Loads, Technical Report, 1988.

[27] UIE (Union Internationale d’Electrothermie), Connection of Fluctuating Loads, Technical Report, 1988.

ADF STATCOM Reduces Flicker at WDI (Comsys AB)

Due to increased use of the local grid, a stricter limit of flicker emission had to be set.
WDI lowered their flicker emission by installing an STATCOM solution.

wdi

Background

WDI (Westfälische Drahtindustrie) is a german industry group founded in 1856 and is the margest steel wire producer in Europe. The company produces steel reinforcement mesh grids at the Salzgitter plant in Germany. The production line comprises various welding equipment, including spot welders from Schlatter AG. Like all powerful spot welders, the abrupt current consumption causes voltage variations, which in turn creates flicker.

Challenge

Due to expansion of the area and increased amount of renewable energy sources, flicker contribution needed to be lowered. Early reference measurement showed flicker levels up to Pst 2 and Plt 1.4. The case was further complicated by a lot of switching activity in the surrounding electrical grid, contributing to higher background flicker and making measurements more difficult. Finally, the flicker will vary with the production type running.

Solution – the high power ADF STATCOM

A solution was delivered to the customer in cooperation with Schlatter AG, who also delivered the welding lines.
An ADF STATCOM consisting of 7 ADF P300W-300/690 was installed. The nominal installed power is 2.5 MVAr. The fully water cooled STATCOM follows the load dynamically. Changes in the production or newly installed equipment does not lead to any adjustment of the compensation system. The ADF P300W units were installed via a dedicated transformer and uses its own medium voltage measurement point.

Result

The flicker level was reduced to Plt 0.6. Current consumption was lowered 25-40% due to reduced reactive power. Voltage dips on the 20 kV rail was lowered from around 500V to around 100V.

 

Key benefits | Spot Welding – Flicker:

  • Pst reduced from 2.0 to 0.6
  • Water cooled solution
  • Complete STATCOM

Flicker level before compensation

wdi before comp

 Flicker level after compensation

wdi after comp

Comsys AB • Ideon Science Park • SE-223 70 LUND • Sweden
Tel: +46 46 286 35 00 • Fax: +46 46 286 35 05
E-mail:info@comsys.se