Ruído onda de tensão & UPS Switching (HIOKI)

Instalação

Monitoramento local : 1-fase 2 fios, 100Circuito V

Problema

Equipment has malfunctioned

Análise

68 “Wave (voltage waveform distortion)” events were recorded during an 18-day measurement period using the following settings. All events are of the same type.

Ruído onda de tensão & UPS Switching 1 Ruído onda de tensão & UPS Switching 2

Próximo, the waveform of each “wave” event was checked, e 2 types of events were found.
Tipo 1: Not switched to a sine wave after the waveform noise
Tipo 2: Switched to a sine wave after the waveform noise
We can assume that the events classified as “switched to a sine wave after the waveform noise” were due to the switching to the UPS output (stand-by system).

It appears that Type 1 has a higher noise level and should be switched to the UPS output. Contudo, Tipo 2 shows a bigger difference in the current waveform when the voltage waveform shows the noise. Portanto, we can assume that a transient overvoltage occurs simultaneously when this event occurs. Infelizmente, the transient overvoltage is not detected, because its threshold is set at 0.480kV (480Em). It is recommended that the threshold be set at 0.07kV (equivalent to 1/2 of the wave peak value) for a 100Vrms circuit

Ruído onda de tensão & UPS Switching 3 Ruído onda de tensão & UPS Switching 4

Fonte : Guia para Medição de Qualidade de Energia, HIOKI E.E. Corporação